During 9 months “Saratovneftegas”, a subsidiary of “RussNeft” has absorbed 380.1 rubles of investments
The company has successfully completed another production modernization project. Reconstruction of complex oil treatment system at Uritski Head Facilities is finished. At present adjustment of technological equipment and automatic systems is being carried out.
More then three years passed from the period of development of the initial project of reconstruction till the date of its implementation. It is only this year, when the new owner – company “RussNeft” – appeared, that the construction went on full speed.
A lot of new equipment was installed: oil-gas separator with fluid output regulating valves, chemical feed block, line heater, water and oil pump stations, tank-truck filling installation, new power substation, torch plant.
The advantages of the reconstruction are, first of all, environmental enhancement in oil producing districts. Due to large-scaled automation working conditions of the operators of Uritski Head Facilities have been considerably improved. Technological process is computer-controlled from the operator’s room, there is no need to stay permanently at the side watching the instrument data.