18.05.2012
"ITAR-ТАSS"
Khanty-Mansiysk. By June 20212 RussNeft to reach comprehensive associated petroleum gas utilization level at Shapshinskaya group of fields /Khanty-Mansiysk Autonomous District/. This was announced about during the press-conference devoted to commissioning of APG processing plant.
Development of Shapshinskaya group of fields is a strategically important project of RussNeft.
Under the development project of Shapshinskaya droup of fields, it’s planned to put into operation the pump station at Nizhne-Shapshinskoye field, gas piston power plant at Verkhne-Shapshinskoye field; by 2012 it’s planned to complete construction of gathering gas pipeline from booster pump station of Verkhne-Shapshinskoye field to booster pump station of Nizhne-Shapshinskoye field, 52 km long.