OAO “Varioganneft” optimizes its oil gathering systems in Tagrinskoe field

21.08.2012 “Neftegazovaya vertical”

Raduzhny (Khmao). OAO “Varioganneft” builds new oil field pipelines in Tagrinsky license area. Construction and overhaul of oil gathering pipelines with an overall length of 15.2 km have been completed in the field.

9.7 km of pipelines have been commissioned in the southern part of the field to include the pipeline from Pad 99 to the Pad 16 tie-in point and the pipeline from Pad 5 to the booster station DNS-1. The implemented project also included construction of pipelines to the newly drilled Pad 107, commissioning of 159 mm and 219 mm OD oil gathering pipelines with overall length of 2.2 km, construction of a 0.5 km 114 mm OD high-pressure water line.

 

5.5 km 273 mm OD pipeline from Pad 64 was commissioned in the North of Tagrinskoe field.

 

Commissioning of these facilities allowed “Varioganneft” to redistribute the produced fluids among the pipelines, decrease the pressure in the pipeline system in the South part of Tagrinsky license area, increase the power efficiency of the oil production and transport of as well as significantly reduce the environmental risks.

 

OAO “Varioganneft” continues implementation of the oil field pipelines optimization and overhaul program in the fields of Variogan oil block.

More news

All Show all

International Forum "Russian Energy Week - 2025"

"Russian Energy Week" is the world's leading industry event, bringing together officials, businessmen and experts to discuss the fuel and energy sector development.

RussNeft reported on the planned stocking of rivers in the Khanty-Mansiysk Autonomous Okrug

The company's press service reported on the completion of work to replenish the Ob River basin with fish resources. 1.1 million young nelma and muksun were released.