Nizhnevartovsk, KhMAO- Yugra. New wells are drilled at Roslavlskoe and Yeguryakhskoye licenses. OAO Aganeftegazgeologiya (subsidiary of NK RussNeft) implements a production drilling program.
New wells are drilled at Roslavlskoye and Yeguryakhskoye license areas of the company.
According to OAO MPG ANGG press-service quoted by Uralinformburo, works are actively performed at Well pad 15 and Well pad 16 of Roslavlskoye field. Six wells out of the existing stock will be deepened down to UV12 formation.
Production drilling started at Well pad 3 of Yeguryakhskoye license area. In the near future, there will be four new wells including two horizontal.
Drilling of eight horizontal wells is scheduled for 2014 at Well pad 12 of Roslavlskoye field. Drilling will penetrate UV12 formation. The overall volume of drilling works will be 32 thousand meters of rock.
The scheduled startup of new wells will allow the company to set up a steady trend for operational performance growth and ensure fulfillment of the company’s annual business plan for hydrocarbons production.