27.12.2013
Tyumenskaya liniya
Nizhnevartovsk, KhMAO. Utilization of APG produced at the fields of OAO MPK Aganneftegazgeologiya (NK RussNeft subsidiary) reached 95%.
This is the result of the planned work at the oilfields of industrial APG utilization infrastructure. A number of operational facilities were commissioned at the fields of the company in 2013 allowing to increase APG utilization according to the level required by the licenses.
Gas compressor station and gas pipeline were commissioned at Zapadno-Mogutlorskoye field. Supply pipeline from Roslavlskoye field DNS 3 Booster Pump Station to Zapadno-Varioganskoye field tie-in gas pipeline and Variogan KS-3 Compressor station was constructed as well. The project was implemented together with OAO NK Varioganneft (NK RussNeft subsidiary). Start-up of the facility allowed utilization of APG from Roslavlskoye and Chukhlorskoye licenses into OOO Yugrapererabotka.
Gas piston generating unit No. 8 was constructed; units No. 9 and No. 10 were constructed at start-up and commissioning stage. Two line oil heaters were reconstructed at the oilfield. Reconstructed energy supply system at Mokhtikovskoye field allowed to reach 6 MW of the planned capacity of gas piston power station.
The joint stock company will continue implementing efficiency increase of APG utilization. Project works and two vacuum compressor units have been scheduled at Mokhtikovskoye field as well as Pump Station-3 at Roslavlskoye field for 2014-2015. Start-up of these facilities will allow up to 99% APG utilization at the fields, as the press-office of Aganneftegazgeologiya reported.